Cold Weather Protocol
Read More

Infrastructure Improvement Plan: 2022 - 2027

Summary
On January 18, 2022, members of Town Staff presented information to the Board of Selectmen about what increased investment in the Town's infrastructure, including roadways, drainage, sidewalks, and more, would look like. The presentation noted that, while there is over $60 million worth of road work to be done at this time, an $18.3 million Town investment, paired with $6.4 million from State and Federal grants, could help the Town take a sizable step towards having roads in excellent condition while not entirely breaking the bank. The proposal suggested that this investment be financed through bonding, which means the Town would borrow funds and make regular payments on those borrowed funds much in the way that one would make payments on a mortgage. Town Staff members presented this information again to the public on five different occasions: at Town Hall on January 31, at the Winchester Center Congregational Church on February 3, at the Little Red Barn Brewery on February 8, at the Senior Center on February 10, and online via Zoom on February 16. Click here to view the presentation that was delivered to the public via Zoom. In April, the Board of Selectmen unanimously approved the infrastructure plan to go to referendum. On May 28, 2022, the Town voted to approve this plan.

2023 is "Year 1" of the Infrastructure Improvement Plan. We currently have work occurring in multiple areas of Town. To learn more, please follow the links below or contact the Department of Public Works at jrollins@townofwinchester.org.


Progress Report


The Need for Investment
On December 20, 2021, Town Staff presented information to the Board of Selectmen about how much work is needed in order to repair Winchester's aging and failing infrastructure. Click here to watch a recording of that presentation, or click here to see the slides that were used as part of that presentation. After this presentation was given, the Board of Selectmen recognized the need for greater investment and asked Town Staff to prepare a follow-up presentation that outlined what greater investment in such infrastructure would look like, and that follow-up presentation was given at the January 18, 2022 Board of Selectmen meeting.

Key Dates
  • Spring 2023: First project kick off, including the Taylor Brook Bridge project, Whiting Street, the Case Avenue Bridge, and more.
  • March 2023: first bond is issued, projects are able to begin.
  • Saturday, May 28, 2022: 8:00 AM to 8:00 PM town referendum was held, allocation was APPROVED.
  • Early May 2022: Town staff hold series of informational sessions with the public.
  • April 2022: Board of Selectmen agree to the plan with minor modifications, plan heads to referendum vote.
  • January 2022: Town staff present plan to Board of Selectmen to fix roads and bridges.

Frequently Asked Questions (FAQ)

Documents & Recordings

Road Detail Sheets

If you are interested in learning more about the projects that are currently a part of the proposed 2022 Infrastructure Investment Plan, please select one of the links below. Each link will take you to a corresponding Project Detail Sheet (PDS) that outlines the project cost, scope, rationale, and more.


Road Projects (18):

Bridge Projects (3):

Other Projects (3):